Location: Lake Hume Village, NSW
Development Progress: Approved
Power Network: Transgrid
Grid Connection Progress: Approved
Large-scale battery energy storage systems will play an important role in the energy transition, by supporting renewable energy and providing stability and firming capacity to the National Electricity Grid. The Hume North BESS is a battery energy storage system that will provide up to 75 megawatts /150 megawatt-hours of on demand power.
The proposed battery will be a standalone project, located approximately 400m away from the existing Hume Hydro Power Station, at the Hume Dam located approximately 20km upstream of Albury-Wodonga.
The site is located on land zoned RU2 Rural Landscape, next to a wastewater treatment plant. Natural vegetation and topography provide a visual screen for the project.
The electricity from the project will be transferred via a new termination into the existing TransGrid 132kV transmission line to further reduce impact, with minimal additional cabling to connect to the line.
Hume North BESS has achieved a significant milestone and was granted its Development Application approval in March 2026.
The planning approval process was initiated in 2024 with the preparation of the Environmental Impact Statement (EIS.) The EIS was submitted in November 2024 and was prepared following extensive community consultation and a series of technical and environmental studies. Following feedback received from the community, key regulatory bodies and both the local and state government, the project incorporated comments into its development application via the submission of a development application modification.
Information on the stages can be found via the NSW Planning Portal:
https://www.planningportal.nsw.gov.au/major-projects/projects/hume-north-battery-en
The Project is classified as a State Significant Development (SSD) and will follow the SSD planning pathway.
We're proud to stand behind efforts that make a difference in our local community. In 2024, the Project supported:
Once the Project is established, we will continue to share the benefits of this project by supporting a community benefit fund for local community groups.
Carbon Reduction
Transition from Coal
Employment
Grid Stabilisation
Development activities are ongoing with preliminary designs, assessments and engagement occurring.
▶ Mid 2023
Neighbour consultation commenced
▶ Late 2023 – Early 2024
Environmental Impact Statement (EIS) compiled and community engagement
▶ Nov 2024
Public exhibition of EIS
▶July 2025
Responses to Submissions
▶March 2026
Project Development Approval Received
▶ July 2026
Grid Connection approval received
▶ Q3-4 2027
Construction begins
▶ Q4 2028
Operational
The timings provided are indicative only, and are subject to change.
North Bess Factsheet - Key Features
North Bess Factsheet - Biodiversity
North Bess Factsheet - Benefits
Foresight wishes to acknowledge the Traditional Owners of the land on which the proposed Hume North BESS is located, the Wiradjuri Nation, and pay our respects to the Elders past, present and emerging.
Get in touch with us for more information or assistance.